On May 22, 2019, the critical portion of site service installation - through horizontal directional drilling under Teston Road, were very smooth and successful. With the SUE GL-A investigation results, Region’s 1800mm and 900mm watermains were actually determined and incorporated in detail design. Hydrovac truck was again on site to expose the watermains during HDD to confirm the exact location.
WPE Engineering Ltd is retained to provide professional civil engineering services for this remarkable community development.